| MS
|
Name
|
WPs
|
Month
|
Verification (KPI)
|
| MS1
|
Project setup phase
|
1,7
|
8
|
Internal management and communication tools in place, website operative, communication, data management and training plans defined (D1.1, D1.2, D7.1, D7.2, D7.3)
|
| MS2
|
Preparation of mini-apps
|
3
|
18
|
Effective co-design with EuroHPC Pilots can start (D3.1)
|
| MS3
|
Flagship code functionalities
|
5
|
24
|
Code version releases with the new functionalities (physics) available repository (D5.1)
|
| MS4
|
Mid-term review meeting
|
1 to 7
|
25
|
Check of the project program development (D1.3)
|
| MS5
|
Exascale code preparation
|
2
|
36
|
Improvements in the flagship codes performance metrics after the second code audit round (D2.2, D2.3)
|
| MS6
|
Exascale pilot deployment
|
4,5
|
42
|
PDs tested successfully (D4.4, D5.2 to D5.10)
|
| MS7
|
Production runs
|
6
|
48
|
SCs executed, EOSC-enabled datasets produced (D6.x)
|
| MS8
|
Community building and Sustainability
|
1, 4, 5, 6, 7
|
48
|
UC services enabled, evaluation exercises with IUB members done, effective liaison with ecosystem initiatives, training completed
|
| MS9
|
Complementary Grants
|
7
|
6
|
Collaboration agreement has been signed
|
| MS10
|
Application deployment
|
4
|
12
|
Applications developed by ChEESE-2P (see Table A1) made available to users of EuroHPC
|